We have signed as many as 3 contracts related to the development of Radom-Sadków airport over the recent weeks. The General Contractor, Heli Factor Sp. z o.o. concluded a contract directly with the Investor, i.e. the “Polish Airports” (“Porty Lotnicze”) State Enterprise, under which it undertakes to complete two investment tasks, in line with the design and build formula:

  1. Drawing up design documentation (Working Design) and carrying out construction and installation works which consist in supply, installation and commissioning of airfield navigation lighting (runway, approaches, taxiways and aprons) for Radom Sadków Airport.
  2. Drawing up design documentation (Working Design) and carrying out of construction and installation works consisting in complete installation of low-voltage networks, supplying power to ILS  and AWOS devices, gates and flow meters.

The value of the Agreement is PLN 9,353,658.54 net and the completion period is 17 months.

We shall perform two further contracts as a subcontractor for:

  • DORACO Sp. z o.o.  Construction Corporation (the General Contractor) – the agreement provides for electrical and teletechnical works as part of the task named “Construction of taxiways and aprons with technical infrastructure on the east side of the airport“. 

The value of the Agreement is PLN 1,697,000.00 net. The completion deadline is October 2021.

  • ROBOZ Piotr Przyłucki, operating in consortium with DROGOMEX Sp. z o.o. (the General Contractor) – the agreement provides for electrical and teletechnical works within the project named “Construction of taxiways and aprons with technical infrastructure on the western side of the airport“.

The value of the agreement is PLN 9,400,000.00 net. The completion deadline is February 2022.

In total, Heli Factor has secured contracts amounting to PLN 20,450,658.54 net (PLN 25,154,310.00 gross). These contracts are of strategic importance to our company and remain in line with our strategy: being the first choice in the performance, supply and integration of airport systems.

We are currently participating in 2 tender procedures to win more contracts from the Investor, providing for performance of the remaining infrastructure for Radom Airport (construction of medium voltage network and sewage system, construction of approaches, etc.) for the total amount of PLN 29,344,467.00 gross. Keep your fingers crossed for us.